The City inspection took place on Friday, May 2. Sheetrock is installed in the "addition" where decorative windows will be. The electrical rough-in is complete. The project is on schedule to be complete around May 28.
1 comment:
Anonymous
said...
Windows look really nice-makes the space attractive/appealing.
Please note: We provide our Construction Blogging commenting feature in order to solicit feedback, debate and discussion on topics of CCMH construction issues. Please keep in mind that civility is a necessary component of productive conversation. All blatantly inflammatory or otherwise inappropriate comments (i.e. vulgarity, marketing, etc.) are subject to rejection and/or removal. Comments will appear if and when they are approved. Thanks for reading, and thanks for participating.