
May 1, 2008
Plumbers will tie in sewer lines, electricians will continue rough in, general contractor will finish framing, backing and soffit installation. Cabinets and windows should be on site today. Building Inspection should happen on Friday. Flooring demo will be completed in the closed area on Sunday 5-4.
Plumbers will tie in sewer lines, electricians will continue rough in, general contractor will finish framing, backing and soffit installation. Cabinets and windows should be on site today. Building Inspection should happen on Friday. Flooring demo will be completed in the closed area on Sunday 5-4.
1 comment:
How long will the construction take?
Post a Comment