Wednesday, November 19, 2008
And the wall came down...
Construction continues to move forward but at least starting tomorrow, patients and guests will be able to sit in a waiting room, and not the hall ways.
Friday, November 14, 2008
Movin right along!
Monday, November 10, 2008
Heat when we need it
Tuesday, November 4, 2008
Home Improvement
The plumbing tie-in to the main sewer line was completed last week. This week workers are in the new edition tiling the new shower rooms--one specifically for decontamination from exposure to hazardous substances or materials. Cabinets for the Trauma room have arrived, and flooring installation should begin next week. New exterior and vestibule doors into the ER are almost done, just in time for more snow.
Tuesday, October 28, 2008
ER floor removal

The main ER beds have been moved and the area they once occupied is now walled off. From behind this temporary wall you can hear the soft roar of the jackhammer. The construction crew is removing the old concrete to run new line under the floor. Surprisingly enough the noise is not as loud as I thought it would be, however still cumbersome, so please bear with us.
Friday, October 24, 2008
I see a bright light...
Monday, October 20, 2008
A little late for snowmelt
Back to the inside of the Emergency Room. Interior painting starts today in the lobby area--you can see ladders stacked up in preparation. Patients and visitors have probably noticed there are no exterior doors at the ER entrance. They were supposed to arrive last week and are expected any time now. Both sets of doors are slated for replacement, and will be done at the same time when they arrive.
Monday, October 6, 2008
Nursing station takes shape
This shows the future nursing station in the ER. Eventually a countertop will run under the recessed lighting and soffits. Drywall was started late last week, and already the area looks much more like it will in the finished version.On another note, Medical Oncology was surveyed (finally) by the state Department of Health last week. A few minor deficiencies were noted, and a plan of correction was sent in. If all goes well, they should be moving into their new digs at the end of the month. Medical Oncology has been housed in the former Childcare department on the third flood since the renovation and expansion began about a year ago.
Tuesday, September 30, 2008
New admitting cubicles
New cubicles in the emergency room are shown from the clerk's point of view. When finished, the new cubicles will be staggered to increase patient privacy. Sheetrock installation should begin this week in this section of the project. Look for new handrails in the ER vestibule that were installed last week.Friday, September 19, 2008
Working on the inside
Monday, September 15, 2008
A look on the inside
Friday, September 12, 2008
Dryvit - EFIS

What is Dryvit? Well I knew nothing about it until today.
More than twenty-eight years ago, Dryvit Systems, Inc. introduced
Dryvit is what the new ER is now covered in. It is really beginning to take shape. Starting Monday the ER entrance will have the other half of the sidewalk done, so no more jack hammering.
The new doors will be installed some time next week. Along with sheet rock and plumbing being done on the inside, the ER is moving right along.
Monday, September 8, 2008
More !*#!* Jackhammering
Friday, September 5, 2008
Health Science Education Center Grand Opening today
Health Science Education Center Grand Opening September 5
A Grand Opening ceremony for the Herbert A. and Dorothy P. Carter Health Science Education Center at the Gillette College will be held Friday, September 5 from 4-6pm.
Construction update
A staging area for current and future construction projects has been created on Burma Avenue north of the hospital. The ground has been leveled and fenced, and will store equipment and materials for the Hospice/Hospitality House, ED construction project and future CCMH expansion project.
Friday, August 29, 2008
Labor for the weekend
The parking lot and sidewalk was finished on the 27th of August.
To day they finish the framing the internal walls
On the 2nd of September the crew will demo half of the ER entrance concrete.
This means that foot traffic will be moved to one side of the entrance, please watch your step.
Among other things being finished, the electrical rough and plumbing rough in will begin.
Keep checking back to stay updated on the progress.
Monday, August 25, 2008
Checking their work
Friday, August 22, 2008
Cooler day

Concrete is still being poured, but as we head into the weekend we are getting some cooler weather. They look to finish the sidewalk next week.
I took some time and snook a peek inside the new ER and this is what I saw.

The new inside is coming around nicely. I can begin to imagine the hustle and bustle of the ER as we expand into our new space. EXCITING!!
Monday, August 18, 2008
Updates
Fire proofing the structural steel will begin today.
Exterior finish of the new structure to start today.
Will finish placing new sidewalk around the new structure today.
Will begin demolition of existing sidewalk adjacent to OSTS.
It will be very busy at the ER entrance and parking will be limited to the far south end and the west side of the ER parking lot.
The entrance will be routed through the north side of the existing entrance. We need to have people park elsewhere if at all possible for the next two weeks. The asphalt is scheduled to be placed on the 26th and 27th. After that time there should be only one more interruption of the ER entry.
Friday, August 15, 2008
Rain, Rain, Rain
Again please use the main entrance to the hospital unless it is an emergancy. Thank you for your cooperation.
Check back Monday for more updates.
Wednesday, August 13, 2008
Steam fried sidewalks

Today they are pouring the concrete on north side of ER for the new steam heated sidewalks. Which I must say are cool in and of themselves. For the past two days workers coiled red tubing around the frame of the new sidewalk. This tubing will be steam heated during the winter to prevent ice buildup. This will be a nice safety feature for patients and staff that use this entrance during the lovely Wyoming winters.
The ER entrance is still cut down to about a third of its original size and now the ER waiting room is almost non-existant, but we are getting by, and we continue to ask for your understand during this time.
Monday, August 11, 2008
Stay off the sidewalk!
Fresh concrete was poured last week for the sidewalks in front of the ER. These sidewalks will be heated for winter snowmelt, which fortunately is a long way off. Be prepared for lots of work going on inside the ER waiting room this week. The waiting room will be partially closed off beginning today to install fireproofing. The seating area will be very limited, so your patience is appreciated. Expect more concrete to be poured on the south and west side of the ER addition to begin today.
Friday, August 8, 2008
Watch out for the sidewalk!
Daily Work
The ER entrance is small compared to normal but it is manageable for all. Please continue to bear with us as we move towards making the ER bigger and better for all.
Monday, July 28, 2008
Cement is flowing like...well, Cement.

The floor is being poured as I type this, which is kind of exciting. For about a month is was just dirt and now it really is taking shape. Plant Operations says that they should start sheet rock and the roof this week also.
Inside three of the new rooms in the ER are getting tiling on them.
Here is an update on our new Medical Oncology suite is waiting on a new fire door then the plans get shipped off to the state for final approval.
Monday, July 21, 2008
Walls

Walls are starting to come a live in the ER remodel.
Floor prep is still being done, so that the new floor can be poured by the end of the week.
Progress is showing as the project keeps moving forward.
On a side note:
CCMH is excited to have New Plant and Facilities Vice President Corey Fedie. Corey began work last week at CCMH. Please welcome him to the CCMH family and our great community.
Thursday, July 17, 2008
The Roof is on

The roof tin is on and the steel is up.
After chatting with Norton Construction, here is the skinny of the ER remodel. Once the plumbing is done the floor will be poured next Tuesday. Tomorrow workers will work on cutting in to the ER waiting room and start finishing that part of the wall. The picture above shows the roof connecting to the existing ER and kind of where the new wall will be assembled. Next week the south wall may begin to be erected, floor permitting.
All in all it is just moving right along. It is really nice just to see progress, it is exciting, well at least for me.
PS: We made the front page of the News-Record, check out the link: PHOTO
Monday, July 14, 2008
Adding Steel
Friday, July 11, 2008
Iron Men?
Monday, July 7, 2008
Tuesday, June 17, 2008
Sunshine and dirt piles
The ER nurses and staff have slowly adjusted to the changes inside the ER. Movement of supply carts and lockers is now expected and become a a little joke - "Where's my locker today? On another floor?" is a common question when a nurse has been off for a couple days.
Remember - use the Walk-in Clinic for minor injuries and illness. They are open Thurs-Mon from 1-9 p.m.
Thursday, June 12, 2008
ER remodel is ER-nder way!

Monday, June 9, 2008
Kitchen is finished!
Now that the kithcen area is done - the ER is really beginning to take shape.
Tuesday, June 3, 2008
Kitchen Serving area move-in day is coming

Friday, May 30, 2008
The serving area is so close to done we can smell it...
Thursday, May 29, 2008
ER Construction = Increased Customer Service

Wednesday, May 28, 2008
Kitchen remodel won't hit deadline

Tuesday, May 27, 2008

Friday, May 23, 2008
Have a safe holiday weekend

The kitchen area is really taking shape, most of the storage areas are complete, the flooring is done and most of the countertops/hard surfaces are installed. This project was projected to be a one-month project and it appears they will hit that target date.
Please be aware - the main lobby outpatient registration desks will be closed on Monday May 26th for the Memorial Day holiday. All patients needing to register should go to the ER.
Thursday, May 22, 2008
Rain, rain go away...


As you can guess - the rain is pooling in the exterior demolition area of the ER remodel. Pumps have been installed to remove the water and in the meantime the contractor has moved inside to install a temporary double door from the ER bay/garage to the ER treatment area. They will also begin framing a dust/firewall in the garage area.
Kitchen
The most exciting thing in the kitchen is the new roll-up doors. If you remember - to close the kitchen area the staff would drag a chain link-like door across both entrances to the serving area. Closure of the serving area will now be more aesthetically pleasing with the roll-up doors. Corian countertops will be installed today and the tile floor will be grouted.
Wednesday, May 21, 2008
ER demolition has begun

Monday, May 19, 2008
Monday...ER begins
Just to remind everyone, ER parking lot will be cut by 5 spaces on the North side by the ambulance bay. Inside remodel will be begin early this week, just keep checking here for further details.
Cafeteria Remodel:
Working on electrical (kind of sounds like a country song) - Wiring continues on the lights. Soffits are hung. Workers are starting to set millwork and installing the oak trim.
Friday, May 16, 2008
Heading into the weekend...
Thursday, May 15, 2008
Let there be light...
Well today's projects include installing lights and hanging soffits. Window trim is going up along with ducts. Both sides of the new wall ceiling grid will be complete and ceiling tile borders will be installed. It is continuing to move right along.
ALSO: Remember that the ER construction begins Monday May 19th. Click here to read more.
Wednesday, May 14, 2008
Ceilings, electricians, windows...oh my!
ER Remodel Starts Monday
Tuesday, May 13, 2008
Painting...
Remember to check back everyday and keep up to date with all things construction here at Campbell County Memorial Hospital.
Monday, May 12, 2008
Thursday, May 8, 2008
Tuesday, May 6, 2008
Friday, May 2, 2008

Soffits and arches at doorways are installed. Plumbing is roughed in. Sheetrock wraps at the windows to be installed today. Window frames scheduled for installation today. Remodel of the serving line counter should begin. Rough-in inspection by City inspector scheduled for the afternoon.
Thursday, May 1, 2008

Plumbers will tie in sewer lines, electricians will continue rough in, general contractor will finish framing, backing and soffit installation. Cabinets and windows should be on site today. Building Inspection should happen on Friday. Flooring demo will be completed in the closed area on Sunday 5-4.
Monday, April 28, 2008
Construction Update






